This building consists of three different sections and ultimately three different projects for different departments within the government. The majority of the space is known as CNSC and houses the majority of the fume hoods for experiments and multiple AHUs and MUAs. The next space is called Zebra with more fumehoods and a dedicated ventilation system. Lastly a small section of the building is made up of a workshop/garage area with dust collectors and unit heater control.
Project Type:
- Retrofit
Installation Type:
- VAV, Fumehoods, MUA’s, AHU’s
Total Area:
- 2,780 m2 (29,923 sq ft)
Equipment Installed:
- 1 MACH-ProWebCom
- 10 MACH-ProSys
- 2 MACH-Global
- 39 MACH-Air
- 1 SMART-Space Controller
- 25 SMART-Sensor LCD
Network:
- EIA-485, Ethernet, LAN
Total System Points:
- 1721
Total BACnet Points:
- 934
Engineering Consultant:
- –